AT&T breaks ground on its 54-acre Plano headquarters campus

The 5AM Lewisville teamFrom the Nov. 13 edition · 1 min read · 4 sources

ShareEmailFacebookX

If you drive the tollway through Plano, you'll soon see a 250-foot tower topped with AT&T's blue logo. The company broke ground Thursday on its 54-acre campus on Legacy Drive, and the groundbreaking marked the installation of the campus's first fiber connection.

AT&T's new campus will be about 2.2 million square feet

Floor area of AT&T's new campus, beside places you know

AT&T's new campus2,200,000 sq. ft.
The former EDS campus2,000,000 sq. ft.Approximately
A football field57,600 sq. ft.end zones included
A Walmart Supercenterabout 180,000 sq. ft.

38 football fields would fit inside AT&T's new campus

Sources: D Magazine, Local Profile

View as table
Floor area
AT&T's new campus2,200,000 sq. ft.
The former EDS campus2,000,000 sq. ft. (Approximately)
A football field57,600 sq. ft. (end zones included)
A Walmart Supercenterabout 180,000 sq. ft.

D Magazine reports the campus will cover 2.2 million square feet with seven office buildings, three parking garages and a welcome center, and will hold about 10,000 employees. Amenities will make up 20 percent of it, including a food hall, a bowling alley and childcare. AT&T wouldn't say what it will spend, but it must spend at least $1.35 billion to get Plano incentives. The site is where the former headquarters came down in an implosion Aug. 9.

  • First two buildings and first garage: projected ready by end of 2028
  • Address: 5400 Legacy Drive, east of the Shops at Legacy
  • Construction crews: upwards of 2,200 workers on site
  • Fiber: about 37 miles of fiber optic connectivity

AT&T's Plano headquarters moves from announcement to construction

  1. JanuaryAT&T announces it picked the Legacy Drive site for its headquarters.
  2. Aug. 9The former headquarters comes down in a controlled implosion.
  3. Nov. 12AT&T breaks ground and installs the campus's first fiber connection.
  4. 2028By the end of the year, the first two buildings and first parking garage are projected to be ready.
  5. 2029Additional campus development continues.

Sources: NBC 5 Dallas-Fort Worth, D Magazine, Local Profile

Read it in the full edition

More from the Nov. 13 edition

Read the edition
All business news
  1. CultureMap DallasYesterday

    Beloved Dallas diner closes its doors and more popular stories, on CultureMap Dallas

    Editor's note: The top Dallas news of the week includes the closures of two longtime Dallas eateries and a surprise appearance by James Talarico. Plus, which Dallas suburb boasts the biggest holiday budget? Get the details on our most popular stories below, then plan a festive weekend via this guide.